Thursday, July 27, 2023

Preparing the Buoy for Deployment

     Marijn came up with the design of the mooring layout for the buoy:


    This morning the Field Team arranged to have a crane truck pick up the CREWS Buoy from the BAMSI warehouse and transport it to the Morgan's Bluff Dock and Harbor.  Shortly thereafter, the Captain and Dive Team arrived with the boat, dive gear, two personnel from the Department of Meteorology, and Skye Minnet.  


Installing the Buoy

     T he Field Team arrived at BAMSI at 7 am to do final preparations of the buoy before the crane truck arrived at 8 am.      Unfortunatel...